How to install ultrasonic vibrator and what details should be paid attention to?
1、Preparation tools: argon arc welding, No.10 hexagon wrench, chrome iron tin wire, 2.5 square high temperature wire, appropriate amount of 2 * 2.5 cable cable, vibrator glue, (wire stripper, casing, tie belt, sandblasting machine, pipe fittings, etc.).
2、Welding screw: calculate the vibrator layout position, weld the screw at the cleaned position, and then clean the screw around, and make sure it is flat, so as to avoid affecting the vibrator installation.
3、Glue configuration: mix the glue evenly according to the specified proportion. (Meirui, aloda and 4030 glue are mixed before bonding, and kmd398 glue is mixed in the bonding process).
4、Installation of vibrator head: apply glue evenly to the bottom of ultrasonic vibrator, and gently twist to squeeze out air and excess glue between the contact surface of transducer bottom and cylinder bottom, so that the vibrator can be integrated with stainless steel more closely.
5、Solidification and condensation: it can be solidified in a place with relatively high room temperature. Wiring can be conducted within 4-8 hours, and the machine can be powered on after 24 hours. No vibration is allowed in the test machine.